Search listings

Building Control (Amendment) Act 2025: What Changed

Updated 3 November 2026 · Land & Property editorial team

The Building Control (Amendment) Act, 2025 was assented to by President Museveni on 19 February 2026 and, according to KTA Advocates, came into force on 19 March 2026. As reported, it raises penalties for building without a permit, makes the National Building Code mandatory, and lets regulators stop or demolish unsafe buildings. The duty to get an occupation permit before moving in already existed. As of November 2026.

Assented
19 February 2026 (Pulse Uganda, KTA Advocates, EPRC)
In force
19 March 2026 (KTA Advocates; Nile Post, 9 April 2026)
Building without a permit
Fines calculated per sq m, or up to five years in prison (Nile Post, quoting the NBRB)
Time limits on permits
Start within 12 months, finish within five years unless extended (Nile Post)
Occupation permit
Section 44 of the 2013 Act, 14 days for the committee to decide

What is the Building Control (Amendment) Act 2025?

It is a law that amends the Building Control Act, 2013, the Act that sets who approves buildings in Uganda and what happens if you build without approval. Parliament passed the Bill in 2025, which explains the year in its title, and the President assented to it on 19 February 2026. Some law firms and news outlets call it the 2026 Act. The Economic Policy Research Centre reports that the President signed it at State House Entebbe together with the Mortgage Refinance Institutions Act and the Valuation Act. KTA Advocates says its aim is to close longstanding gaps in the Building Control Act, restructure oversight institutions and tighten the permit regime, and that it came into force on 19 March 2026.

Our checking has limits. We could read the 2013 Act, but we could not find the text of the amending Act online. Everything below about what changed comes from news reports, a law firm alert and a government agency's public statement, and we say who said what. Section numbers, exact fine amounts and transitional rules should be confirmed against the Act in the Gazette or by a lawyer before you rely on them.

What changed in building law in 2026?

The table sets the 2013 baseline, which we read in the Act, against the 2026 changes as reported. The baseline fines use the Act's value of UGX 20,000 per currency point.

Topic2013 Act (baseline)2026 amendment, as reported
Building without a permitFine up to 50 currency points (UGX 1,000,000) or up to two years, or both (s.34)Fines calculated per sq m, or up to five years in prison (NBRB, 9 April 2026)
Negligence causing a site accidentFine up to 288 currency points (UGX 5,760,000) or up to 12 years, or both (s.45)Fines up to UGX 10 million or up to 12 years (NBRB, 9 April 2026)
Occupying before an occupation permitFine up to 24 currency points (UGX 480,000) (s.44(3))Amended amount not confirmed. Pulse says the requirement already existed
Time limitsStart within 12 months, finish within 60 months (s.38)Start within 12 months, finish within five years unless extended; deferred applications must be completed within 12 months or they expire
OversightNational Building Review Board (NBRB) and district and urban Building CommitteesNBRB board reduced from 16 to nine members; local Building Committees reduced to five technical experts reporting quarterly
StandardsNational Building Code under s.46Compliance with the National Building Code is now mandatory

The same Nile Post report, quoting the NBRB's Executive Secretary Flavia Bwire at the Uganda Media Centre, says the NBRB can issue stop or evacuation orders for unsafe buildings and enter sites to check compliance, and that Local Building Committees can demolish or evacuate structures built in breach. It adds that new construction technologies and materials may be approved if they are assessed and certified, and that regulations covering demolition, new technologies and enforcement are still to be drafted. In practice that means the headline rules are in force but the detailed regulations are not all in place.

KTA Advocates and the Nile Post both describe the amendment as imposing harsher penalties. Neither source, in the pages we could read, gave the per-square-metre rates. If you need to know what you would pay for a specific building, ask a lawyer for the rate in the Act.

Do I need inspection before moving in?

Yes. This part is not new, but 2026 has made it more visible. Section 44(1) of the 2013 Act requires the owner of a completed building to notify the Building Committee of practical completion and to apply for an occupation permit. Section 44(2) gives the committee fourteen days to examine the building and issue the permit or refuse it with written reasons. Pulse Uganda, writing in April 2026, reports that the requirement existed before the amendment and that what changed is the enforcement climate. It adds that applications can be filed through the Building Industry Management System (BIMS), and that there are full, temporary and partial permits.

For the full process, documents and the KCCA fee, read Occupation Permit in Uganda: When You Need One. If you are a buyer, ask for the permit before you pay the balance, because moving into an uncertified building can expose you personally.

What must owners, developers and buyers do now?

This is a practical checklist based on what is reported. It is not legal advice.

  • If you are about to build: get the approved plan and building permit first, from KCCA or your local authority. See Building Plan Approval in Kampala. Use a registered architect and engineer. KCCA and the Architects Registration Board said in May 2026 that unqualified people posing as architects and engineers are linked to poor workmanship and building collapses, and that new enforcement measures have been introduced against them.
  • If you have a permit and are building: note the reported time limits. Start within 12 months and finish within five years, or apply for an extension in writing. Keep the jobcard up to date.
  • If your building is finished: notify the Building Committee and apply for the occupation permit. Do not allow tenants in before it is issued.
  • If you are a developer of apartments: you carry the obligations above for the whole building, and the unit titles come through the condominium route. See condominium property act and New Apartment Developments in Kampala, 2026.
  • If you are buying: ask for the approved plan, the permit and the occupation permit, and have a lawyer check them. Compare prices on House Prices in Kampala and Wakiso (Our Listings), and browse house listings.
  • If your building is old and unapproved: ask your local authority what regularisation route exists, because we found no published one. Do not extend or sell on the assumption that nothing will be enforced.

Costs may also rise. See cost to build a house in Uganda for what we could verify on building costs. This Act is separate from the land laws, which are covered in Land Act sections. When you need to see a building and its paperwork, book an escorted site visit.

What are the penalties and who enforces them?

Enforcement has three layers. First, the Building Committee of the district or urban authority (for example KCCA in Kampala) approves plans, inspects work and, as reported, can now demolish or evacuate buildings that breach the law. Second, the National Building Review Board oversees the system and, as reported, can order unsafe buildings to stop or be evacuated. Third, the courts impose the fines and prison terms.

The reported penalty headlines are fines per square metre or up to five years' prison for building without a permit, using prohibited methods or continuing after a permit has expired, and fines up to UGX 10 million or up to 12 years' prison where negligence causes an accident. The Act, the NBRB said, also makes compliance with the National Building Code mandatory. Because these are reports and not the Act's text, check the exact wording for your case.

Property buyers should remember one more link in the chain. The Physical Planning Act, 2010, section 33, separately makes developing land without development permission an offence, and says dealings connected with that development are null and void. Both laws can apply to one building.

Frequently asked questions

What changed in building law in 2026?

The Building Control (Amendment) Act, 2025 was assented to on 19 February 2026 and, per KTA Advocates, took effect on 19 March 2026. As reported by the NBRB, it raises penalties, makes the National Building Code mandatory, adds stop and evacuation orders, lets Building Committees demolish unsafe buildings, and sets permit time limits. We could not read the amended text, so confirm details with a lawyer.

Do I need inspection before moving in?

Yes. Section 44 of the Building Control Act, 2013 requires the owner of a completed building to notify the Building Committee and apply for an occupation permit, and the committee must examine the building within 14 days. Occupying a building before the permit is issued is an offence. A partial permit can allow use of a safe, finished part.

Is it the 2025 Act or the 2026 Act?

Both names are used. The Bill was passed in 2025 and is titled the Building Control (Amendment) Act, 2025, while the President assented to it on 19 February 2026, and some law firms and media call it the 2026 Act. They are the same law. Check the Act in the Gazette for the official citation.

What is the penalty for building without a permit now?

Under the 2013 Act the fine was up to 50 currency points (UGX 1,000,000) or two years in prison. The NBRB said on 9 April 2026 that the amended law sets fines calculated per square metre or up to five years in prison. We could not read the amended section, so ask a lawyer for the current rate.

Does the amendment affect houses I already own?

It can. A completed house without an occupation permit is in breach of section 44 of the 2013 Act, and enforcement is now stricter according to Pulse Uganda and the NBRB. If your house has no permit, ask your local authority how to apply, and keep your approved plan and inspection records ready.

Sources

  1. Building Control Act, 2013 (Act 10 of 2013), sections 34, 38, 44 to 46 and Schedule 1, Republic of Uganda, hosted by KCCA (accessed 2026-11)
  2. How the Valuation Act 2026 and the Building Control Amendment Act 2026 will affect the built environment, KTA Advocates (accessed 2026-11)
  3. NBRB unveils tough new building law, warns of stricter enforcement, Nile Post via AllAfrica, 9 April 2026 (accessed 2026-11)
  4. Moving into your new home: when and how to get Uganda's occupancy permit, Pulse Uganda, April 2026 (accessed 2026-11)
  5. Strengthening Uganda's housing and construction ecosystem: economic implications of the new 2025 laws, Economic Policy Research Centre (accessed 2026-11)
  6. KCCA, Architects Registration Board meet over building permit delays, Nile Post via AllAfrica, 19 May 2026 (accessed 2026-11)
  7. Physical Planning Act, 2010, section 33, Republic of Uganda, hosted by KCCA (accessed 2026-11)